Dam Projects
No. Project |
Project |
Status |
1 |
Project of Raising Timah Tasoh Dam, Perlis (Phase 2): Package 1 - Construction of Western Spillway. (Contract No: JPS/IP/BRE/04/2011) |
Physical Progress = 100.00%/100.00% (31/8/2015) Financial Progress = 77.43%/99.19% (31/8/2015) |
2 |
Upgrading Kangar - Padang Besar Road, Lencongan Barat Timah Tasoh Road, Sahabat - Kg Aman Road and All Related Works Under Project of Upgrading Timah Tasoh Dam, Perlis, Phase 2 - Package 3 (Contract No: JPS/IP/BRE/02/2013) |
Physical Progress = 42.00%/77.00% (31/8/2015) Financial Progress = 30.58%/70.40% (31/8/2015) |
3 |
Construction of Stilling Basin, Upgrading Outlet Structure and Semandong Irrigation Intake Under Project of Upgrading Timah Tasoh Dam, Perlis, Phase 2 -Package 2 (Retender - Contract No: JPS/IP/BRE/03/2013) |
Physical Progress = 90.00%/88.00% (31/8/2015) Financial Progress = 90.32%/90.00% (31/8/2015) |
4 |
Construction of protection bund and internal drainage system and all related works at Mukim Kg Tasoh under project of Upgrading Timah Tasoh Dam, Perlis Phase 2 - Package 4 |
Physical Progress = 25.00%/29.00% (31/8/2015) Financial Progress = 5.52%/13.12% (31/8/2015) |
Last Updated 2017-12-04 11:47:32 by Administrator